The last few months have shown
significant progress, and we love seeing the community come to
life! Nearly all the houses in Stage 1 have been completed internally and
Stage 2 homes will follow shortly this month. We are seeing more kitchens,
bathrooms, and pergolas being completed, with landscaping commencing
as we speak. Road sub-base and services have commenced in Stage 1 in
preparation for the roads, driveways, and paths.
Services location for the Public Domain works have been completed
allowing the commencement of physical works to road widening, a
channelised right-hand turn, kerb, and guttering. The kiosk substation has
been installed, with the substation scheduled for energisation in mid-June.
Civil works and services installation to Stages 3 to 5 will continue throughout
June.